tweaked this to have a bit more structure so we get things we need done finished...
authorcharles
Wed, 26 Feb 2014 01:25:43 +0100
changeset 3 a9f055821a83
parent 2 0762b478cb3d
child 4 f42a511dcd4c
child 11 68efbad8ae7c
tweaked this to have a bit more structure so we get things we need done finished...
longdesc/TODO.md
--- a/longdesc/TODO.md	Wed Feb 26 01:13:11 2014 +0100
+++ b/longdesc/TODO.md	Wed Feb 26 01:25:43 2014 +0100
@@ -3,34 +3,42 @@
 ## Emails
 
 - Reply to [EOWG](http://lists.w3.org/Archives/Public/public-html-a11y/2013Sep/0037.html) Chaals
-- Reply to [Matt Turvey](http://lists.w3.org/Archives/Public/public-html-a11y/2013Dec/0083.html) Chaals
 - Reply to [UAWG](http://lists.w3.org/Archives/Public/public-html-a11y/2014Jan/0068.html) Chaals
 
+
+
 ## Publication
-
-- Verify no open exclusion opportunities
+### Before going to the TF
 - Write Document Status Section
-- Write Exit Criteria (Mark is Drafting)
-- Record Decision to request the transition
-- Schedule Meeting with Director
+- Write Exit Criteria (Mark is Drafting) But chaals wrote a draft and shared it w/ Mark.
+### In the Task Force
+- Get TF then WG approval of the exit criteria
+- Record Decision to request WG request the transition
+### When the TF has agreed
+- Get WG to request the transition
+
+- Schedule Meeting with Director, HTML chairs as needed
+### Needed for Director's meeting
 - Report of important changes to the document
 - Record  Objections
 - Patent disclosures
+- Verify no open exclusion opportunities
 - Evidence that the document satisfies group's requirements
 - Evidence that dependencies with other groups are met
 - Evidence that the document has-  received wide review
 - Evidence that issues have been formally addressed
 - Implementation Report (Mark is Drafting)
 - Prepare Spec to pass pubrules
-- Create a Publication Schedule
 - Verify that transition requirements have been met
+
 - Send Transition Request
-- Create Agenda
+- Create Agenda (This should just be "step through the transition request" which has all the things that need to get checked)
 - Reserve Teleconference Bridge
-- Choose a scribe
-- Transition Meeting Prep/Practice
+- Transition Meeting Prep/Practice (Don't bother with this. The "director" who sounds a lot like Ralph will check through the things required, which should be in the transition request, and if we're good, says "OK". If you are really concerned, ask PLH to have a quick look first).
 - Transition Meeting
-- Director Approves Transition Request
+
+### When we are approved for Proposed Rec
+- Create a Publication Schedule
 - The Team Contact reviews theĀ (Team-only) pre-publication steps.
 - Send a pub request
 - install the document in its final location
@@ -38,4 +46,9 @@
 - Send DRAFT transition announcement to Comm Team
 - Public Mailing List
 - Team Only Mailing List
-- The Facilitators fwd announcement to WG and TF-
\ No newline at end of file
+- The Facilitators fwd announcement to WG and TF-
+
+##DONE
+
+- Reply to [Matt Turvey](http://lists.w3.org/Archives/Public/public-html-a11y/2013Dec/0083.html) Chaals
+- Chaals will scribe transition call.